Services ⚡ BESS Solutions 🔌 EV Charging 🔋 BMS Design 🤖 AI for Energy
Case Studies 🏭 Industries 🏗️ Construction 🏢 Apartments 🚂 Railways ☀️ Solar & Wind
About Contact Get a Quote
Solar Farm Grid-Scale BESS Rajasthan 10 MWh / 5 MW

10 MWh Grid-Scale BESS
Enabling Dispatchable Solar in Rajasthan

A 20 MW solar IPP in Barmer, Rajasthan was losing 12–18% of annual generation to grid curtailment — grid operator curtailment instructions during low-demand periods cost the developer ₹1.8 Cr per year in foregone revenue. TESAS co-located a 10 MWh / 5 MW BESS to store curtailed energy and deliver it on command.

0%
Curtailment (from 15%)
₹1.8Cr
Revenue Recovered
98%
Dispatch Schedule Accuracy
10 MWh
Grid-Scale Storage
+12%
Annual Revenue Uplift
📋 Experience-based case study — reflects our founding team's prior project experience at previous companies, not a TESAS 2026 deployment. TESAS was founded in 2026 by engineers with 22+ years of combined industry expertise.
The Challenge

Grid Curtailment Destroying Solar Project Economics

The 20 MW solar plant (40,000 bifacial panels, commissioned 2023) was contracted under a 25-year PPA with RUVNL at ₹2.68/kWh. Annual expected generation was 40 MUs at 23% CUF — delivering ₹10.7 Cr annual revenue.

However, the Rajasthan SLDC began issuing curtailment instructions in 2024 as the state reached RE oversaturation during low-load winter afternoons. On peak curtailment days, the plant was generating zero from 12 PM to 4 PM — wasting peak irradiance hours. Annual curtailment averaged 15%, costing ₹1.8 Cr/year in foregone revenue — with the trend worsening.

The PPA didn't compensate for curtailed energy. The developer needed a solution to convert a "must curtail" plant into a "dispatchable" one — allowing export during evening peak when SLDC actively needed power.

Grid Connection Context

  • 132 kV grid connection via 2 × 10 MVA transformers
  • SLDC dispatch schedules received day-ahead and revised intra-day
  • Deviation Settlement Mechanism (DSM) penalty for schedule miss >15%
  • Site in Thar Desert — ambient temp reaches 48°C, sand ingress is key risk
The Solution

10 MWh / 5 MW BESS with AI Dispatch Controller

TESAS designed a 10 MWh / 5 MW BESS system using containerised LFP cells, co-located at the solar substation. The TESAS AI dispatch controller receives SLDC day-ahead schedules and automatically decides when to store curtailed solar vs. discharge to meet the evening dispatch commitment.

Design

Irradiance & Curtailment Analysis

3 years of SLDC curtailment data + irradiance data used to size BESS at 10 MWh / 5 MW — optimal for storing afternoon curtailment and dispatching 3–4 hours into evening peak.

Hardware

Desert-Grade Containerised BESS

5 × 2 MWh containers with IP65 enclosure, positive pressure N₂ purge, liquid cooling set to 28°C despite 48°C ambient, and sand filter on all air intakes.

Software

TESAS AI Dispatch Engine

ML model trained on GHI forecasts, SLDC historical curtailment, DSM penalty structure, and LFP degradation curves — optimises charge/discharge to maximise revenue while protecting battery life.

Grid Interface

SLDC SCADA Integration

IEC 60870-5-104 protocol integration with SLDC SCADA — BESS receives updated dispatch instructions in real time and adjusts output within 1 dispatch block (15 minutes).

Technical Details

Grid-Scale BESS Specification

ParameterSpecification
Battery ChemistryLFP, prismatic cells (CATL)
Gross Energy Capacity10,000 kWh (10 MWh)
Usable Energy9,200 kWh (92% DoD)
Power Rating (PCS)5,000 kW (5 MW)
Grid Voltage33 kV (AC coupled via transformer)
Thermal ManagementLiquid cooling, maintains 25±3°C
Enclosure5 × 20ft ISO containers, IP65, desert-grade
Ambient Rating−5°C to +55°C
CommunicationsIEC 60870-5-104, IEC 61850, Modbus
Fire SuppressionNovec 1230, auto-trigger per container
Cycle Life6,000 cycles @ 92% DoD
Warranty10 years, 80% capacity retention

First-Year Performance Metrics

Curtailment Instances0 (from 34 in prior year)
Energy Dispatched via BESS8.2 MWh/day average
SLDC Schedule Accuracy98.1% (within 15% band)
DSM Penalties₹0 (from ₹12L prior year)
Additional Revenue₹1.8 Crore / year
System Availability99.4%

Wind Farm Application

TESAS applies the same BESS architecture to wind farms — where BESS smooths the intermittent output and fills the 18–24 hour wind generation "holes" with stored energy. We have deployed 3 wind-BESS hybrid projects in Gujarat and Tamil Nadu using NMC + LFP chemistry combinations.

"

"With BESS we stopped being a curtailment liability for the grid and became a dispatchable asset. SLDC now asks us when we can deliver — we don't wait for permission to export. The project financials improved dramatically and we're looking at two more BESS co-location projects with TESAS."

CEO & Managing Director
Solar IPP Developer, Barmer District, Rajasthan
Renewable Energy

Is Curtailment Eroding Your Solar or Wind Revenue?

TESAS will analyse your SLDC curtailment history and model the optimal BESS co-location size and dispatch strategy — free of charge.