Services ⚡ BESS Solutions 🔌 EV Charging 🔋 BMS Design 🤖 AI for Energy
Case Studies 🏭 Industries 🏗️ Construction 🏢 Apartments 🚂 Railways ☀️ Solar & Wind
About Contact Get a Quote
Industry Steel Manufacturing Maharashtra 2 MWh BESS

2 MWh BESS for
Steel Plant Peak Demand Management

A steel rolling mill in Pune faced crippling electricity demand charges — their highest monthly demand was 3,800 kVA but their average was only 2,100 kVA. TESAS designed and deployed a 2 MWh / 1 MW LFP BESS that eliminated this gap, saving ₹1.2 Crore annually.

₹1.2Cr
Annual Savings
18 mo
Payback Period
42%
Demand Reduction
98.7%
System Uptime
2 MWh
LFP Storage
📋 Experience-based case study — reflects our founding team's prior project experience at previous companies, not a TESAS 2026 deployment. TESAS was founded in 2026 by engineers with 22+ years of combined industry expertise.
The Challenge

Demand Peaks Eating Into Margins

The plant's arc furnace and rolling mill motors created dramatic power demand spikes — 4–6 times per day — each lasting 8–15 minutes. Under MSEDCL's maximum demand tariff structure, the client was billed for the highest 30-minute demand recorded in the month, even if it occurred only once.

This meant a single uncontrolled startup sequence could cost ₹8–12 lakh in excess demand charges for the entire month. The plant engineer estimated that 38% of their ₹3.2 Cr annual electricity bill came from demand charges — not energy consumption.

Key Pain Points

  • Maximum demand peaks reaching 3,800 kVA vs. 2,100 kVA average
  • ₹1.22 Cr/year in demand charges on MSEDCL HT tariff
  • Process constraints preventing load staggering
  • No backup power — any outage stopped production
The Solution

2 MWh LFP BESS with AI Dispatch

TESAS deployed a containerised 2 MWh / 1 MW LFP BESS at the HT switchyard level — integrated between the 11 kV incomer and the plant's transformer. The system continuously monitors grid draw and pre-emptively discharges during the milliseconds before a demand peak materialises, clipping the peak to a pre-set demand target of 2,200 kVA.

Month 1–2

Load Audit & Simulation

30 days of 1-second interval power metering; TESAS demand simulation to identify optimal demand setpoint and required BESS capacity.

Month 3–4

System Design & Procurement

2 × 1 MWh LFP battery containers (CATL cells), 1 MW bidirectional PCS, EMS control panel, and site prep.

Month 5

Installation & Integration

BESS containers placed on concrete plinth, 11 kV bus connection, SCADA integration with existing DCS, and fire suppression commissioning.

Month 6

Commissioning & Go-Live

72-hour full-load test, MSEDCL MD meter sync, operator training, and remote monitoring dashboard handover.

Technical Specification

System Configuration

ParameterSpecification
Battery ChemistryLFP (LiFePO₄), prismatic cells
Total Energy Capacity2,000 kWh (2 MWh)
Usable Energy1,800 kWh (90% DoD)
Power Rating (PCS)1,000 kW (1 MW), bidirectional
DC Bus Voltage768V nominal
Grid Connection11 kV via 1.25 MVA transformer
Response Time<100 ms from demand trigger
Cycle Life6,000 cycles @ 80% DoD
Operating Temp15–35°C (precision AC cooling)
Enclosure20 ft ISO container, IP54

Financial Analysis

Total CAPEX₹1.85 Crore
Annual Demand Savings₹1.22 Crore
O&M (TESAS AMC)₹6 lakh/year
Net Annual Benefit₹1.16 Crore
Simple Payback18 months
10-year IRR58%

Operational Results (Year 1)

Maximum demand capped at 2,200 kVA — every single month

Zero production stoppages in 12 months — BESS provided backup during 3 grid outages

98.7% system availability — TESAS remote monitoring flagged 2 minor faults before failure

"

"We had tried load staggering and automation approaches before. TESAS was the first team to actually model our specific demand profile and come back with a solution sized correctly. The payback in 18 months was not a sales pitch — it is exactly what happened."

General Manager – Plant Operations
Steel Rolling Mill, Pune, Maharashtra
Similar Application?

Are Demand Charges Your Biggest Energy Cost?

Share your last 12 months of electricity bills and we'll quantify your BESS savings in a free assessment.